Project : Abu Cluster
Location : Abu A Platform
TSE Rep. : Muhammad Amin bin Hj Che Hassan
Client : Petronas Carigali Sdn Bhd
Date of Service : 17 October 2008 until 21 October 2008
17/10/2008 (Friday)
- Mob to Abu A
- Attend safety briefing
- Site work preparation
18/10/2008 (Saturday)
- Internal wiring checks for PZT-0101A, PZT-0101B, PZT-0601 and SDV-0601.
Finding: Tag at PZT-0101A need to change to TB-B +123, TB-B -124 and PZT-0101B to TB-B +125, TB-B -126.
- Continuity checks for instrument South West well area with Local Engineering personal. For production line two pressure transmitter PZT-0101A and PZT-0101B. For gas lift line is a PZT-0601 and SDV-0601. All pressure transmitter and shutdown valve solenoid A and B success for continuity checks.
- Continuity check for instrument Abu Kecil 2 well area with Local Engineering personal. For production line two pressure transmitter PZT-0104A and PZT-0104B. For gas lift line is a PZT-0604 and SDV-0604. All pressure transmitter and shutdown valve solenoid A and B success for continuity checks.
19/10/2008 (Sunday)
- Functional test for instrument South West well area with Local Engineering personal. For production line two pressure transmitter PZT-0101A and PZT-0101B. For gas lift line is a PZT-0601 and SDV-0601.
- Inject pressure at PZT-0101A and PZT-0101B for gets HH (5680kpag) and LL (410kpag). Set point HH (PZAHH-0101A, PZAHH-0101B) and LL (PZALL-101A, PZALL-0101B) triggered at SIS and alarms display at DCS. Test successful.
- Activate solenoid A (SXV-0601A) and solenoid B (SXV-0601B) for SDV-0601. Finding: Voltage from marshalling cabinet MDF4500B for solenoid A (SXV-0601A) and solenoid B (SXV-0601B) drop from 24V to 12V only. Although voltage drops, solenoid A and B still function SDV-0601 can open.
- Functional test for instrument Abu Kecil well area with Local Engineering personal. For production line two pressure transmitter PZT-0104A and PZT-0104B. For gas lift line is a PZT-0604 and SDV-0604.
- Inject pressure at PZT-0104A and PZT-0104B for gets HH (5680kpag) and LL (410kpag). Set point HH (PZAHH-0104A, PZAHH-0104B) and LL (PZALL-104A, PZALL-0104B) triggered at SIS and alarms display at DCS. Test successful.
- Activate solenoid A (SXV-0604A) and solenoid B (SXV-0604B) for SDV-0604. Finding: Voltage from marshalling cabinet MDF4500B for solenoid A (SXV-0604A) and solenoid B (SXV-0604B) drop from 24V to 12V only. Although voltage drops, solenoid A and B still function and SDV-0604 can open.
20/10/2008 (Monday)
- Functional test for valve SSV-0104 and SCSSV-0104 at Abu Kecil 2 well area with Local Engineering personal. Witness by operation (Mr.Rafidi).
- Sequence to functional test SSV-0104 and SCSSV-0104 at Abu Kecil 2 well area:
- Apply MOS at PZT -0104A and PZT -0104B.
- Open SCSSV-0104. Pressure at PZT-0041B increased around 32000kpag.
- Open SSV-0104. Pressure at PZT-0041A increased.
- Closed SSV-0104.
- Disable MOS at PZT -0104A and PZT-0104B
- Pressurize at PZT-0104A and PZT-0104B to get a normal pressure.
- Open SSV-0104. Successful.
- Pressurize at PZT-0104A and PZT-0104B to get a HH setting.
- SIS triggered HH set point and SSV-0104 closed.
- Pressurize back at PZT-0104A and PZT-0104B to get a normal pressure
- Open SSV-0104.
- Pressurize at PZT-0104A and PZT-0104B to get a LL setting.
- SIS triggered LL set point and SSV-0104 closed.
- Functional test for valve SSV-0104 and SCSSV-0104 successful.
21/10/2008 (Tuesday).
- Report writing
- Demob to Kerteh.